(c) Supervision o the constructon of 2No. Road packages in Jimeta-Yola.
Total Budget
₦500,000,000
Project Description
(c) Supervision o the constructon of 2No. Road packages in Jimeta-Yola.
Project Timeline
Planning
Dec 28, 2025Tender
(c) Supervision o the constructon of 2No. Road packages in Jimeta-Yola.
Award
Awarded to Supplier
Nov 30, -0001Contract
Contract signed
Planning Details
Project planning and budget information
Budget Amount
₦500,000,000
Budget Source
-
Rationale
Tender Information
Procurement tender details and documents
(c) Supervision o the constructon of 2No. Road packages in Jimeta-Yola.
Value
₦0
Procurement Method
Open
Start Date
Jul 07, 2020
End Date
Jul 17, 2020
Tender ID
ocds-adamawa-2025-255-tender-076
Involved Parties
All parties involved in the project
No Parties Information
Parties details have not been added to this project
Awards
Project awards and contract assignments
(c) Supervision o the constructon of 2No. Road packages in Jimeta-Yola.
Award Value
₦47,544,781
Awarded To
Salima Engineering
288
Contracts
Contract agreements and modifications
(c) Supervision o the constructon of 2No. Road packages in Jimeta-Yola.
Contract Value
₦47,544,781
Start Date
Nov 30, -0001
End Date
Nov 30, -0001
Contract ID
ocds-adamawa-2025-255-contract-283
Period
0 days