ocds-adamawa-20...

(d) Supervision of the Construction of Army Barrack-Mayo-Ine-Mayo-Belwa Road.

Works & Energy Development
Yola North
Updated Dec 28, 2025
Total Budget
₦500,000,000

Project Description

(d) Supervision of the Construction of Army Barrack-Mayo-Ine-Mayo-Belwa Road.

Project Timeline

Planning

Dec 28, 2025

Tender

(d) Supervision of the Construction of Army Barrack-Mayo-Ine-Mayo-Belwa Road.

Award

Awarded to Supplier

Nov 30, -0001

Contract

Contract signed

Project Information

OCID
ocds-adamawa-2025-256
Status
Created
Dec 28, 2025
Budget Source
Not specified

Project Stats

0
Parties
1
Tenders
1
Awards
1
Contracts
Export Project Data

Planning Details

Project planning and budget information

Budget Amount
₦500,000,000
Budget Source
-

Rationale

Tender Information

Procurement tender details and documents

(d) Supervision of the Construction of Army Barrack-Mayo-Ine-Mayo-Belwa Road.

Value ₦0
Procurement Method
Open
Start Date
Jul 07, 2020
End Date
Jul 17, 2020
Tender ID
ocds-adamawa-2025-256-tender-077

Involved Parties

All parties involved in the project

No Parties Information

Parties details have not been added to this project

Awards

Project awards and contract assignments

(d) Supervision of the Construction of Army Barrack-Mayo-Ine-Mayo-Belwa Road.

-0001-11-30 00:00:00
Award Value
₦74,381,183
Awarded To

Salima Engineering

288

Contracts

Contract agreements and modifications

(d) Supervision of the Construction of Army Barrack-Mayo-Ine-Mayo-Belwa Road.

(d) Supervision of the Construction of Army Barrack-Mayo-Ine-Mayo-Belwa Road.
Contract Value
₦74,381,183
Start Date
Nov 30, -0001
End Date
Nov 30, -0001
Contract ID
ocds-adamawa-2025-256-contract-284
Period
0 days